Schedule

While the grant proposals are being evaluated, the project team is continuing through its engineering and environmental (NEPA) phases with a particular focus on finding additional cost savings. Permitting and right-of-way acquisition are scheduled to begin in mid-2021. Construction would start in 2023 and go through 2025. Without grant funding, additional project redesign may be needed to meet budgeted funds, with a new project schedule.

Sign up for email updates about the project.

Project schedule 2020 through 2025 shows preliminary engineering through summer 2021, environmental permitting until winter 2023, right of way acquisition summer 2021 through spring 2023, and construction starting by spring 2023 and ending in late 2025.